Project Details
Creative Movement Studio
| Project #: | 12-05 |
| Detailed Status: | Project Closed |
| Building Gross Sq. Ft: | 9,597 |
| Campus: | TTU Lubbock |
| Budget | |
| Board Approved Budget: | $2,200,000 |
| Adjusted Budget: | $2,212,500 |
| Final Cost: | $2,164,040 |
| Schedule | |
| Construction Start Date: | 02.03.2012 |
| Project Completion: | 01.30.2013 |
| Project Team | |
| Program Director: | Rick Richeda |
| Contractor: | Western Builders of Amarillo |
| Design Professionals: | Condray Design Group; Fanning, Fanning & Associates |
| CM Agent: | N/A |
| Artist: | Mark Chew |
| Art Title: | The Fire Inside |
| Description | |
| The project will renovate the gymnasium currently associated with the Exercise Sciences Center for the relocation of the dance program. The space will include accommodations for the Âé¶¹¹ÙÍø Tech Cheer and Pom Squads. The scope will include a large (3,500 sf) studio, a small (2,000 sf) studio, a 2,100 sf classroom, men and women locker areas, office suite and associated storage. | |